Project overview

The project includes, but isn’t limited to:

  • Swing Bridge repairs and rehabilitation
  • New swing bridge driving surface
  • New sanitary system
  • New storm system
  • New and upgraded watermains
  • New traffic signals
  • New traffic lights
  • New pedestrian crossings
  • New sidewalks
  • New landscape features
  • New road alignment and parking configurations
  • New Town Hall Ramp

aerial image of Huntsville and Diggin Downtown logo

Anticipated Construction Schedule

  • Stage 1 - March – May 30, 2021
  • Stage 2 - May 31 – July 30, 2021
  • Stage 3 - July 31- September 15, 2021
  • Stage 4 - September 16 – November 15, 2021
  • Stage 5 - Spring 2022
  • Final Completion: End of May, 2022