2011 Construction Projects

The chart below lists all of our current construction and reconstruction projects across Huntsville:

Clearwater Lake Road - Town of Huntsville Project
 Fall 2010Spring 2011Summer 2011Summer 2012 
Chip Brush and Saplings from Road Side and DitchesPulverize the RoadHigh Float is to be Applied to the RoadSlurry Seal is to be Applied to the Road
Clear Ditches 3" to 6" lift of 'A' Gravel to be Applied   
Remove Large Rocks from the Road Base Stabilize the Road Base with Calcium  
Remove Logs from the Road Base    
Replace Cross Culverts Under Road (As Required)    
Replace Driveway Culverts (As Required)   
Grade the Shoulders of the Road    

 

Brunel Road (Main to Florence) - District of Muskoka Project
 Start DateWeek of July 11th 2011
 Scope of ProjectReconstruct Storm Sewers, Sanitary Sewers, Water Mains, Sidewalks and Road
 Project Manager CC Tatham & Associates
Construction CompanyFowler Construction Company