2011 Construction Projects
The chart below lists all of our current construction and reconstruction projects across Huntsville:
| Clearwater Lake Road - Town of Huntsville Project |
| Fall 2010 | Spring 2011 | Summer 2011 | Summer 2012 |
| Chip Brush and Saplings from Road Side and Ditches | Pulverize the Road | High Float is to be Applied to the Road | Slurry Seal is to be Applied to the Road |
| Clear Ditches | 3" to 6" lift of 'A' Gravel to be Applied | | |
| Remove Large Rocks from the Road Base | Stabilize the Road Base with Calcium | | |
| Remove Logs from the Road Base | | | |
| Replace Cross Culverts Under Road (As Required) | | | |
| Replace Driveway Culverts (As Required) | | | |
| Grade the Shoulders of the Road | | | |
| Brunel Road (Main to Florence) - District of Muskoka Project |
| Start Date | Week of July 11th 2011 |
| Scope of Project | Reconstruct Storm Sewers, Sanitary Sewers, Water Mains, Sidewalks and Road |
| Project Manager | CC Tatham & Associates |
| Construction Company | Fowler Construction Company |